A presswood pallet line reaches rated output around day 90, not week two. The press arrives calibrated; the plant around it does not. This page sets out the five acceptance gates we write into a commissioning contract and the exact test conditions behind them, so you can compare quotations on the same basis. The full arithmetic sits in our guide, Rated Output Is a Day-90 Number.

The five acceptance gates

Test conditions to fix in writing

A rated-output figure tested on someone else’s fiber is a marketing number. Name the conditions in the contract: the moisture band (the working target sits near 9%), screen size, binder percentage, ambient temperature and which mold is fitted. Every extra point of water adds 30–40 seconds to a cycle and pulls output down by more than a tenth, so “rated output” without a moisture band is not a testable figure.

What the ramp actually costs

On a dual-station line rated at 176 pallets per shift, a normal 55% / 75% / 90% ramp across three months costs about 7,306 pallets you never invoice — roughly €58,000–88,000 of revenue and 99 tonnes of fiber. First-week scrap on a new mold and unfamiliar fibre runs 8–12%, settling under 1% by month four. Dating the gates above is how you pull that number back.

Contract your fibre before you commission. Sawdust is a by-product of sawmill running hours: when lumber prices fall, mills cut shifts and residue supply tightens exactly as a new line ramps up. Fix a monthly tonnage, a moisture spec and a contamination limit first.

Want the gates applied to your own residue? Send 50–100 kg of your sawdust or shavings and we will press it on a real mold. Start with the presswood pallet machine page for tonnage and configuration, or contact our engineering team to book a trial. Tooling choices are covered in the palletsbiz mold library.

FAT, SAT and first article: what gets signed before handover

Commissioning is the last gate in a contract that should have named its first gate months earlier. A presswood pallet line needs three distinct acceptance tests, and mixing them is how buyers end up paying for a machine they cannot prove. Our full guide, What Is Acceptance Testing on a Presswood Pallet Line?, breaks each one down.

Tie the shipping payment to the FAT report and the final payment to a signed SAT. Load claims should trace back to ISO 8611-1:2025 test data, not a brochure. Want these gates applied to your own residue? Send 50–100 kg and we will press it on a real mold.

One more gate for hot sites: retest at your summer ambient

The five gates above assume a temperate hall. A line shipped to a site above 40°C needs a sixth condition written into the day-90 performance test. Tonnage is pressure times piston area and does not change with the weather. Cycle time does: ISO VG 46 oil thins from 46 cSt at 40°C to about 23 cSt at 60°C, and a 12% output loss takes a 105,600-pallet line down to roughly 93,000.

Add one line to the contract: repeat the rated-output test at 40°C ambient or at the agreed summer design temperature, and log the oil temperature curve through the shift. Specify the cooler, a 60°C alarm and a 70°C trip, panel air conditioning, and a spare cooler core on the first shipment. The arithmetic and the four RFQ questions sit in Your 1,600-Ton Rating Was Written at 20°C. Jeddah Runs at 46°C.